• Actual language: english
  • switch to Greek

Country

United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

go here Segments

Processes

get link Steps

Barriers

Indicators

Compare Results

Last update: 13.05.2014

National Contact Point: HELLENIC ASSOCIATION OF PHOTOVOLTAIC COMPANIES (HELAPCO) - Stelios Psomas
(spsomas(at)otenet.gr, info(at)helapco.gr)

The installation of PV systems on commercial buildings follows a relatively easy process, especially since mid-2010, when new legislation came into force lifting ... (Unhide text)
 
This segment covers commercial systems with an installed capacity 10-100 kWp. As of winter 2011, installations on listed buildings are not allowed. From August 2012 till April 2014 there was a suspension of new applications for this segment, and only old applications holding a grid connection contract and having already applied for a Power Purchace Agreement could proceed while the authorization freeze was in place.

 
Waiting Time
 
Active time
On average, 95% of total project duration is waiting time
 
Grid connection and relevant permitting accounts on average for 69% of all waiting time

 
Legal-administrative Labour Requirements
 
Non Legal-administrative Labour Requirements
Legal-administrative related labour requirements account for 14% of total labour for the project

 
Legal-administrative costs
 
Other costs
Legal-administrative requirements account on average for 21% of overall developement costs (excluding PV equipment)
 
Non-construction labour accounts for 34% of total labour cost