United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

Segments

get link Processes

Steps

Barriers

Indicators

Compare Results

Last update: 13.05.2014

National Contact Point: HELLENIC ASSOCIATION OF PHOTOVOLTAIC COMPANIES (HELAPCO) - Stelios Psomas
(spsomas(at)otenet.gr, info(at)helapco.gr)

This segment comprises half of ... (Unhide text)
 
Since June 2010, a "Production Licence" is no more needed for systems up to 1 MWp, while most ground-mounted systems up to 500 kWp are exempted from environmental permitting. The key bottleneck until recently was the grid connection offer. From August 2012 till April 2014, a suspension on new licensing of this segment was in place. Only old applications holding a grid connection contract and having already applied for a Power Purchace Agreement could proceed while the freeze in licensing was in place.

 
Waiting Time
 
Active time
On average, 95% of total project duration is waiting time
 
Grid connection and relevant permitting accounts on average for 49% of all waiting time

 
Legal-administrative Labour Requirements
 
Non Legal-administrative Labour Requirements
Legal-administrative related labour requirements account for 2% of total labour for the project

 
Legal-administrative costs
 
Other costs
Legal-administrative requirements account on average for 1% of overall developement costs (excluding PV equipment)
 
Non-construction labour accounts for 19% of total labour cost