• Actual language: english
  • switch to Greek

Country

United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

get link Segments

follow url Processes

go to link Steps

Barriers

Indicators

Compare Results

Last update: 13.05.2014

go here National Contact Point: HELLENIC ASSOCIATION OF PHOTOVOLTAIC COMPANIES (HELAPCO) - Stelios Psomas
(spsomas(at)otenet.gr, info(at)helapco.gr)

... (Unhide text)
 
For being eligible to incentives (feed-in-tariffs) when installing a small residential PV system (<10 kW), a part of the building's hot water needs must be covered by renewable energy sources such as solar thermal systems. The only authorities involved in authorization are the local branch of the Distribution Network Operator (HEDNO, which issues a grid-connection offer) and the Public Power Corporation (PPC) (or any other electricity retailer) with which a “compensation agreement” is being signed. As of winter 2011, installation of rooftop systems on listed buildings is not allowed.

Filing of an application for drawing up of a Connection Agreement

Filing of an application for drawing up of a Connection Agreement with the regional branch of HEDNO.
The application states that the Connection offer is accepted.
 
Authorisation request
Authorisation request
Step Difficulty:  Low
 
Authority NameHEDNO
SpecialistsEngineer