United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

Segments

Processes

Steps

Barriers

Indicators

Compare Results

Last update: 13.05.2014

National Contact Point: HELLENIC ASSOCIATION OF PHOTOVOLTAIC COMPANIES (HELAPCO) - Stelios Psomas
(spsomas(at)otenet.gr, info(at)helapco.gr)

... (Unhide text)
 
For being eligible to incentives (feed-in-tariffs) when installing a small residential PV system (<10 kW), a part of the building's hot water needs must be covered by renewable energy sources such as solar thermal systems. The only authorities involved in authorization are the local branch of the Distribution Network Operator (HEDNO, which issues a grid-connection offer) and the Public Power Corporation (PPC) (or any other electricity retailer) with which a “compensation agreement” is being signed. As of winter 2011, installation of rooftop systems on listed buildings is not allowed.

 
Waiting Time
 
Active time
This step requires a visit to the electricity provider for initiating the process for a Power Purchace Agreement which the provider usually signs after 1-2 weeks
 
It normally takes a week of waiting for a call by the electricity provider to the customer announcing that a Power Purchace Agreement is ready for signing

 
Legal-administrative Labour Requirements
 
Non Legal-administrative Labour Requirements
Labour at this step is related to installer's staff accompanying the customer to the electricity provider's office for arranging a Power Purchace Agreement

 
Legal-administrative costs
 
Other costs
During this process, there are no non-legal-administrative costs incured.
 
Costs at this step are related to installer's staff accompanying the customer to the electricity provider's office for arranging a Power Purchace Agreement