United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

click Segments

enter site Processes

Steps

go here Barriers

free cyber sex chat room Indicators

Compare Results

Last update: 19.06.2014

click National Contact Point: eclareon GmbH - Edoardo Binda Zane
(ebz(at)eclareon.com)

The latest estimations (November 2013) of the amount of installed PV ... (Unhide text)
 
The project lifecycle of industrial ground-mounted systems takes 69 weeks on average and cases of processes lasting up to three years have been reported. About half of this time is calculated as waiting time, that is time spent waiting for an answer from authorities or to connect to the grid. Usually, operators of industrial ground-mounted systems make use of the renewables obligation quota system instead of the feed-in tariff, following a drop of the latter in 2011.

 
Waiting Time
 
Active time
Usually the overall project takes about 44 weeks.
 
There are usualy 20 weeks of waiting time.

 
Legal-administrative Labour Requirements
 
Non Legal-administrative Labour Requirements
270 man-hours on average are required to comply with legal-administrative requirements

 
Legal-administrative costs
 
Other costs
Costs are on average 300.000 €.
 
Costs can reach up to 7.000.000 €, but are usually around 2.500.000 €.