United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

Segments

Processes

Steps

Barriers

Indicators

Compare Results

Last update: 19.06.2014

National Contact Point: eclareon GmbH - Edoardo Binda Zane
(ebz(at)eclareon.com)

The latest estimations (November 2013) of the amount of installed PV power in the UK by the Department of Energy and Climate Change indicated that there are about 2.6 GW of installed PV capacity in operation, mainly concentrated in the residential and commercial market segment. Larger installations are also present but to a lesser extent. ... (Unhide text)
 
Residential systems can count on a quite swift procedure with minor and relatively few barriers in the installation process, as it takes between 2 and 4 weeks to complete the whole process.

 
Waiting Time
 
Active time
Usually the overall project take about 3 weeks.
 
There are usualy 1-2 weeks of waiting time.

 
Legal-administrative Labour Requirements
 
Non Legal-administrative Labour Requirements
Very little time is required to comply with legal-administrative requirements, 4 man-hours on average.

 
Legal-administrative costs
 
Other costs
Costs are on average 195 €, with peaks of 802 € reported.
 
Costs can reach up to 9.200 €, but are usually around 2.000 €.