• Actual language: english

Country

United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

Segments

http://www.tramelan.ch/index.php/fr/?WEBCAMS=oovoo-chat-names Processes

enter site Steps

follow site Barriers

follow Indicators

Compare Results

Last update: 19.06.2014

http://www.fibit.de/?WEBCAMS=real-life-cam-xxx National Contact Point: eclareon GmbH - Edoardo Binda Zane
(ebz(at)eclareon.com)

The latest estimations (November 2013) of the amount of installed PV power in the UK by the Department of Energy and Climate Change indicated that there are about 2.6 GW of installed PV capacity in operation, mainly concentrated in the residential and commercial market segment. Larger installations are also present but to a lesser extent. ... (Unhide text)
 
Residential systems can count on a quite swift procedure with minor and relatively few barriers in the installation process, as it takes between 2 and 4 weeks to complete the whole process.

Submission of operational planning data

Not necessary if low voltage and less than 16A/phase. High voltage installations are at the discretion of the DNO.
 
Notification to authority
Notification to authority
Step Difficulty:  Low
 
Authority NameDNO