United KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomUnited KingdomPolandPolandBelgiumSwedenSwedenSwedenSwedenSwedenNetherlandsNetherlandsSloveniaPortugalPortugalPortugalPortugalPortugalGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceGreeceSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainSpainBulgariaItalyItalyItalyItalyItalyCzech RepublicSlovakiaGermanyGermanyGermanyGermanyAustriaFranceFranceFranceFranceFranceFranceFrance

Legend

 
smart
 
fair
 
improvable
 
troublesome
 
bad
Severe barrier

Database Help

Segments

see url Processes

Steps

Barriers

Indicators

Compare Results

Last update: 19.06.2014

National Contact Point: eclareon GmbH - Edoardo Binda Zane
(ebz(at)eclareon.com)

The latest estimations (November 2013) of the amount of installed PV power in the UK by the Department of Energy and Climate Change indicated that there are about 2.6 GW of installed PV capacity in operation, mainly concentrated in the residential and commercial market segment. Larger installations are also present but to a lesser extent. ... (Unhide text)
 
Residential systems can count on a quite swift procedure with minor and relatively few barriers in the installation process, as it takes between 2 and 4 weeks to complete the whole process.

DNO offer

DNO makes an offer to accept multiple installations specifying any costs to be borne by the developer and timescales for completion of DNO work within 30 days
 
Other administrative action/step
Other administrative action/step
Step Difficulty:  Low
 
Authority NameThe local Distribution Network Operator (DNO)
SpecialistsNo formal need for specialist but developer might find it useful to obtain Engineering help.